On July 17, 2014, the Supreme Court of Ohio handed down a merit decision in Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp.,2014-Ohio-3095. In a 5-2 opinion authored by Justice Kennedy, the Court held that a contract for work performed by a subcontractor for a general contractor which contains a provision that

Update: On July 17, 2014, the Supreme Court of Ohio handed down a merit decision in this case.  Read the analysis of that decision here.

On November 5, 2013, the Supreme Court of Ohio heard oral argument in the case of Transtar Electric, Inc. v. A.E.M. Electric Services Corp., 2013-0148.  At issue in this

Update: On July 17, 2014, the Supreme Court of Ohio handed down a merit decision in this case.  Read the analysis of the decision here.

Read the analysis of the oral argument here.

On November 5, 2013, the Supreme Court of Ohio will hear oral argument in the case of Transtar Electric, Inc. v. A.E.M.